Your Construction Loan Is Maturing. What Are Your Options?
Five ways out when the loan comes due before the property is ready for permanent debt, and how to choose among them.
Why this is happening to so many owners
Most construction loans were sized on a schedule: build in 18 to 24 months, lease up in 12, refinance at a set rate. When construction runs late, lease-up is slower than planned or permanent rates are higher than underwritten, the loan matures before the property can support a takeout large enough to repay it. The property is not failing. The timing is off.
Option 1: Extend the loan you have
Read the extension section of the loan agreement first. Most construction loans have one or two extension options of six to twelve months, each with conditions. The usual ones are:
- No default, and written notice inside a set window (often 30 to 90 days before maturity).
- Construction complete, with a certificate of occupancy.
- A minimum occupancy, debt service coverage or debt yield test.
- An extension fee, commonly 0.25% to 0.50% of the loan.
- Replenished interest reserve and, on floating-rate loans, a new interest rate cap.
If you miss a test, the lender can still agree to extend. Expect a request for a partial paydown, added guaranty or cash management in return. An extension is usually the cheapest option, and it buys the time the other options need.
Option 2: Refinance into a bridge loan
A bridge loan replaces the construction loan with two to three years of floating-rate debt sized for a property that is still leasing. Debt funds and some banks will lend against properties that are 60% to 80% occupied. The rate is higher than permanent debt, but the loan is usually non-recourse apart from standard carve-outs, which releases the completion and repayment guaranties you signed for construction. That release is often worth more than the rate difference.
Option 3: Go straight to permanent debt
If the property is close to stabilized, a permanent loan may be within reach now:
- Fannie Mae and Freddie Mac generally look for about 90% occupancy held for 90 days, and both have programs for properties that are close to that mark.
- HUD Section 223(f) no longer requires three years of operating history. HUD removed that rule in 2020, so a newly built property can apply once it shows stabilized operations. The process is slow, so many owners pair it with a short bridge loan.
- Banks and life insurance companies will often close a five to ten year loan faster than either, at lower leverage.
Option 4: Bring in new capital
When the new loan is smaller than the old one, something has to fill the gap. The choices are your own equity, a new equity partner, preferred equity, mezzanine debt, or in many states C-PACE financing (long-term financing for energy and water-related building components, repaid through the property tax bill). Each needs the senior lender’s consent, and each has a cost that should be compared against selling.
Option 5: Sell
A sale during lease-up prices the property on today’s income, so the buyer gets paid for finishing the job. It is the right answer when the gap is too large to fill at a sensible cost. It should be a decision you make, not one made for you by a maturity date.
How to choose
Work it as arithmetic. Take the property’s in-place net operating income and size a new loan at the lender’s tests. For example, a property with $2.0 million of net operating income and a lender requiring 1.25 times coverage at a 6.5% rate on 30-year amortization supports roughly $21 million of debt. If the construction loan balance is $25 million, the gap is $4 million, and the question becomes which source fills $4 million at the lowest cost and with the least loss of control.
Then set the calendar. A bank extension takes weeks. A bridge loan takes 45 to 75 days. Agency loans take 60 to 90 days. HUD takes considerably longer. Count backward from maturity and you will see which options are still open.
What not to do
- Do not wait for the lender to raise the subject. Lenders have the most flexibility when the borrower comes early with a plan.
- Do not let the loan go past maturity without a signed extension or forbearance. Default interest and a guaranty claim change the negotiation.
- Do not take the first bridge quote. Terms on extension tests, prepayment and recourse vary more than the rate does.
Construction loan coming due?
Send the loan documents, the rent roll and the maturity date. We will return the realistic options, what each one costs and how long each takes.
Request a preliminary analysisThis material is for general educational purposes only and does not constitute legal, tax, or financial advice. Program rules and market terms change and apply differently to specific properties; confirm current requirements with your lender and qualified counsel. Gibson Capital Advisors is a debt advisory firm and does not make loans.